Algonquin Public Right-of-Way ADA Transition Plan

The Village of Algonquin is completing an ADA Transition Plan for Algonquin sidewalks, multi-use paths, and intersections. The goal of this plan is to improve accessibility for everyone in Algonquin, including people with disabilities. A key priority of this plan will be to improve access to parks and other key public community destinations.

The ADA Transition Plan will:
  • Build on existing data to complete a self-evaluation of sidewalks, multi-use paths, and intersections
  • Identify locations along sidewalks, multi-use paths, and at intersections that limit accessibility
  • Create an implementation roadmap that helps prioritize projects that improve accessibility
  • Provide a clear path for providing feedback to the Village in the future regarding accessibility
  • Incorporate public feedback provided by the community throughout the project

Plan materials and surveys will be posted on this website as available.

Get Involved

Do you use sidewalks or multi-use paths in Algonquin? Are there spots you find difficult to access? We want to hear from you!

A community survey will be available from June 3 through July 8, 2025.

This 16-question survey includes an interactive map where you can pinpoint specific locations that may present accessibility challenges. Your feedback will help the Village prioritize future improvements.

The survey is available in multiple languages:

Paper copies of the survey are available at:

Questions?

If you would like to receive project updates or to provide comments to the project team, email ADATransitionPlan@algonquin.org.

Project Timeline

Below is a timeline for the ADA Transition Plan project, outlining major milestones such as data collection, community engagement, and development of the final plan.

Project Milestone Date
Gather Data & Review Existing Conditions Spring 2025 – Fall 2025
Public Survey Summer 2025
Self-Evaluation Summer/Fall 2025
Stakeholder Outreach Ongoing
Develop ADA Transition Plan Fall 2025 – Spring 2026
Draft ADA Transition Plan for Public Review Winter 2026
Public Open House Winter 2026
Anticipated Plan Approval Spring 2026*