October marks the second month of construction on Hanson Road. Construction crews completed main line storm sewer and box culvert installation. The roadway and base layers south of Harnish Drive have been completely removed and crews have begun removal of base layers on Hanson Road north of Harnish Drive.
In November, storm sewers will be installed with site grading and base roadway/curb installation to occur on Hanson Road between Edgewood Drive and Harnish Drive. Please visit the Village Construction Projects page for more information on the Hanson Road Reconstruction project.