North Harrison Street Reconstruction (Algonquin Hills Phase 4) back  

Construction Update
None

Project Description
 
This project will rebuild North Harrison Street from just north of Ericson Marina to just north of Deerpath Road at the Village limits. The project will remove the existing roadway, and install a new pavement cross section. The project also includes, curb & gutter, sidewalk on the West side of the roadway, and an upgraded storm water collection system.
 
Press Releases
 
None at this time
 
Project Schedule
(Weather Permitting)
 
June 2010 - Project Began
December 2010 - Road Open to Traffic
May 2011 - Project Substantially Completed.  Minor items to be completed in summer 2011.
Summer 2011 - Project Complete
 